Crane Island the Balder
Offices on top of crane island the Balder
For 3 days, Algeco's team and the team of our client Heerema Marine Contractors worked together in shifts, day and night, to erect the units, with a surface area of 936m², on top of this crane island 'The Balder'.
The job included the installation of:
- offices
- changing rooms
- a coffee corner
- sanitary facilities
"Friday started, Monday my people are working in these units. No words, but deeds",
says Nico de Bruijn, senior asset equipment manager at Heerema.
- Project specifications
-
BrancheIndustry
-
Construction time3 days
-
Number of unit(s)52
It is a turnkey project. Algeco provided all the facilities, such as
- water supply and drainage
- power supply by means of generators
- lockers for 600 people
- furniture
"Whenever there were small changes to be made during the project, Algeco was there to make them happen." A satisfied customer said.
Start date: 4 weeks after request.